خانه » وبلاگ » Double Girder Gantry Crane Installation Guide

Double Girder Gantry Crane Installation Guide

2026-09-14

General Overview

This guide specifies the standard installation procedures, الزامات ایمنی, and commissioning steps for double girder gantry cranes. It applies to industrial outdoor and indoor double girder gantry cranes used for material handling in factories, پورت ها, و سایت های ساختمانی. All installation work must be performed by certified professional technicians in strict accordance with manufacturer specifications and national crane safety standards. Unauthorized modification of installation procedures is prohibited to avoid equipment failure, آسیب ساختاری, or safety accidents.

Double girder gantry crane installation guide

Double girder gantry crane installation guide

آماده سازی قبل از نصب

1. بازرسی سایت & Foundation Verification

اول, inspect the installation site to ensure the ground foundation meets the load-bearing requirements of the double girder gantry crane. Check the flatness, سختی, and levelness of the foundation, and confirm there is no subsidence, کرک, or uneven settlement. Verify the installation spacing, track center distance, and overall dimension of the site match the crane’s design parameters. Clean up obstacles on the installation route and working area to ensure sufficient space for hoisting, مونتاژ, and subsequent operation.

2. نصب ریل & بازرسی

Install the crane running rails strictly according to the design drawings. Fix the rails on the foundation embedded parts, adjust the rail levelness, صراط مستقیم, and gauge deviation to meet standard requirements. پس از نصب, conduct a comprehensive inspection: check rail connection firmness, weld quality, and end clearance; ensure no deformation or dislocation of the rails. Record all inspection data for subsequent acceptance reference.

3. Component Checking & Tool Preparation

Unpack all crane components including double main girders, پاهای حمایت کننده, واگن های انتهایی, traveling wheels, hoist trolley, سیستم کنترل الکتریکی, اتصال دهنده ها, and safety accessories. Carefully check each part for manufacturing defects, تغییر شکل, زنگ زدگی, یا آسیب, and verify the quantity and model of components are consistent with the delivery list. Prepare professional installation tools, hoisting equipment (auxiliary cranes, زنجیر, قلاده), measuring instruments (laser level, آچار گشتاور, متر نواری), and safety protection supplies.

4. Safety Preparations

Set up warning zones and safety barriers around the installation site, and post safety warning signs. All construction personnel must wear safety helmets, safety belts, and other protective equipment. Conduct pre-installation safety technical disclosure to clarify operation specifications, risk points, and emergency disposal measures. Confirm the power supply of the site is stable and grounded reliably to ensure safe electrical operation.

Double girder gantry crane installation guide

Double girder gantry crane installation guide

Main Mechanical Structure Installation

1. Ground Pre-Assembly

Complete partial pre-assembly of components on the flat ground to reduce high-altitude operation risks. Assemble the two main girders as a whole structure according to the assembly marks, fasten all connecting bolts with a torque wrench to reach the specified torque value. Install the walking platform, نرده ها, and trolley running track on the main girders, and check the flatness and firmness of the track surface. Then assemble the supporting legs and end carriages into integrated parts respectively.

2. Supporting Leg & End Carriage Installation

Use qualified auxiliary hoisting equipment to lift the assembled supporting leg and end carriage assemblies vertically, and place them accurately on the reserved installation position of the running rails. Adjust the verticality, تراز بودن, and spacing of the supporting legs strictly, fix the traveling wheel boxes on the rails, and ensure the wheels are completely attached to the rail surface without deviation or suspension. Temporarily fix all connecting parts to prevent displacement during subsequent girder installation.

3. Double Main Girder Hoisting & Fixing

Adopt integral hoisting method for the assembled double main girders. Hang the slings at the designated lifting points of the girders to ensure uniform stress and balance during hoisting, and avoid tilting or structural deformation. Slowly lift the main girder assembly to the design height, align the connecting holes with the top of the supporting legs accurately, and carry out butt joint installation. After precise alignment, install and tighten all high-strength bolts in sequence, and use a laser level to recheck the levelness and span deviation of the main girders to ensure compliance with design standards.

4. چرخ دستی & Hoisting Mechanism Installation

Place the assembled hoist trolley stably on the trolley track of the double main girders, adjust the trolley wheel gap and running parallelism to ensure flexible and jitter-free movement. Install the lifting mechanism, steel wire rope, بلوک قرقره, and hook group in strict accordance with the mechanical assembly drawings. Check the winding direction and tightness of the steel wire rope to ensure no strand disorder, extrusion, یا پوشیدن. Install buffer devices, limit stoppers, and anti-derailment devices at both ends of the trolley track.

Double girder gantry crane installation guide

Double girder gantry crane installation guide

Electrical System Installation

1. Electrical Component Installation

Install the main electrical control cabinet, trolley control box, resistance box, and operating device (pendant control or cab control) at the designated positions. Fix all electrical boxes firmly with shock absorption measures to prevent vibration damage during crane operation. Install travel limit switches, lifting height limit switches, محدود کننده های اضافه بار, and other safety electrical accessories, and ensure all sensor components are installed accurately and fixed reliably.

2. سیم کشی & Grounding

Lay cables strictly in accordance with the electrical wiring diagram, arrange cables neatly, and fix them with cable clamps to avoid dragging, extrusion, and friction damage. Connect L1, L2, L3 power lines, neutral line N, and protection grounding line PE correctly, and tighten all copper wire terminals firmly to ensure good electrical contact. Complete the grounding connection of the crane metal structure, and test the grounding resistance to ensure it meets safety standards, preventing electric leakage accidents.

3. Circuit Inspection

After wiring completion, conduct a comprehensive circuit inspection. Check for wrong wiring, missing connection, virtual connection, and short circuit risks. Verify the phase sequence of the power supply to ensure the walking and lifting directions of the crane are consistent with the control operation. Inspect the insulation performance of all circuits to ensure no insulation damage or electric leakage hidden dangers.

Double girder gantry crane installation guide

Double girder gantry crane installation guide

Debugging & راه اندازی

1. No-Load Debugging

Switch on the power after confirming all mechanical and electrical installations are qualified. Conduct no-load operation debugging: operate the crane’s longitudinal traveling, trolley transverse traveling, and lifting mechanism respectively. Check whether each mechanism runs smoothly without abnormal noise, jitter, or stuck phenomenon. Test the sensitivity and reliability of all limit switches, دستگاه های بافر, and safety protection functions, and adjust the limit stroke to the standard range.

2. تست بارگذاری & کالیبراسیون

After qualified no-load debugging, carry out graded load tests according to standard procedures, از جمله 25%, 50%, 75%, 100%, و 125% rated load tests. During the test, check the structural deformation of the main girders and supporting legs, the operating stability of each transmission mechanism, the braking performance of the brake system, and the accuracy of the overload protection device. Record all test data, and adjust and calibrate unqualified items until they meet the standard requirements.

3. Overall Performance Inspection

Inspect the overall operation coordination of the crane, confirm the synchronous operation of each mechanism, accurate control response, and reliable braking. Check the tightness of all connecting bolts, the lubrication state of transmission parts, and the integrity of safety accessories. Eliminate all installation defects and hidden troubles to ensure the crane’s overall performance meets design and safety operation standards.

Final Acceptance & Safety Notes

1. Completion Acceptance

Sort out all installation records, inspection data, گزارش های تست, and component qualification certificates to form a complete acceptance document. Conduct final acceptance jointly by the construction team, supervision party, and user party. The crane can only be put into formal operation after passing the overall acceptance and obtaining the crane use qualification certificate.

2. Daily Safety Operation Notes

Operators must receive professional training and hold valid certificates before taking up their posts. Strictly abide by the crane operating specifications, prohibit overload operation, oblique pulling, and random limit operation. Conduct daily inspection and regular maintenance of the crane’s mechanical structure, سیستم الکتریکی, and safety devices to ensure long-term stable and safe operation of the equipment.

3. Post-Installation Maintenance

After installation and commissioning, lubricate all rotating and transmission parts comprehensively. Check and fasten all loose fasteners again. Clean the equipment surface, sort out installation tools and residual materials on site, and complete site cleaning and finishing work.

Double girder gantry crane installation guide

کارخانه ویهوا

مقاله قبلی:
نه بیشتر, این در حال حاضر جدیدترین مقاله است

Get Solution & Price Right Now!

ما برای بازخورد شما ارزش قائل هستیم! لطفاً فرم زیر را تکمیل کنید تا بتوانیم خدمات خود را متناسب با نیازهای خاص شما تنظیم کنیم.

نام:
* ایمیل:
واتساپ / شماره تلفن:
محل پروژه:
* پیام:

آخرین نظرات

تسفای ملیس سعید:
40 مونتاژ چرخ دستی جرثقیل سقفی تن دو تیر با لوازم جانبی کامل برقی و مکانیکی
ریکاردو آگیلار سعید:
برای پروژه بازسازی جرثقیل, ما باید یک واحد تهویه مطبوع را در وب سایت شما نصب کنیم، ما این راه حل را پیدا کردیم. ظرفیت خنک کننده: 2.5 KW a 7.0 KW (8,500 الف 24,000 BTU/ساعت) ظرفیت گرمایش (اختیاری): 2.0 KW a 6.0 KW Fuente de alimentación: 24در D.C. / 110V y / 230V y / 415V y, 50/60 هرتز (نیاز را مشخص کنید) یخچال: R410A یا اکولوژیک R134a
گفت:
ظرفیت 50 TON AKS ARALIK 40 متر 12 METRE KANCA ALTI RAY BOYU 250 متر, 2 جرثقیل پورتال QTY
هوبرت پاتینو سعید:
جرثقیل های Weihua عزیز, با سلام از طرف GPANTEC SAC, واقع در لیما, پرو. ما می خواهیم قیمت یک بلوک 12 تنی تولید شده توسط شما را درخواست کنیم.. کد مرجع محصول یا شماره سریال جرثقیل سقفی می باشد 110220.075, و مدل بلوک قاپ 12/2t-40M می باشد. تصویری از بلوک قاپ مورد درخواست ما پیوست شده است. مقدار درخواستی یک کیت می باشد. منتظر توجه شما عزیزان هستیم. ارادتمند.
لا گرانژ سعید:
آقا یا خانم عزیز, ما در حال حاضر به دنبال تامین کننده ای برای سیستم ریلی هادی محصور برای بالابرهای زنجیره ای الکتریکی هستیم که در مسیرهای مونوریل کار می کنند.. لطفا قیمت خود را برای شرایط زیر ارائه دهید: Project Scope Quantity: 8 independent lines Length: 80 meters per line Total length: 640 meters Electrical Requirements Supply voltage: 400 VAC Frequency: 50 Hz Number of poles: 4 جریان نامی: حداقل 40 A Application Electric chain hoist Safe Working Load (SWL): 2,500 kg One hoist per line Outdoor industrial installation Protection Requirements Minimum protection class: IP43 Preferred protection class: IP54 or higher Please include in your offer Conductor rails Power feed sections Joint assemblies End caps Hangers and support brackets Current collectors Expansion sections if required Complete accessory list Documentation Required Technical datasheets. تایید کتبی رتبه حفاظت IP سیستم کامل. گواهی های آزمایش یا گزارش های آزمایشگاهی که مطابقت با الزامات IP43/IP54 را نشان می دهد. مراجع نصب جرثقیل مشابه, مونوریل, یا برنامه های بالابر. لطفاً نیز اشاره کنید: زمان تحویل. کشور سازنده. دوره گارانتی. اینکوترمز. تفکیک قیمت در هر خط و برای پروژه کامل. پیشاپیش ممنون, انبار سدریک

موارد مرتبط

واتساپ

با ما تماس بگیرید

برای به دست آوردن اطلاعات محصول و نقل قول های موجود در WhatsApp روی دکمه کلیک کنید.

نقل قول
واتساپ
تحقیق