» ブログ » Double Girder Gantry Crane Installation Guide

Double Girder Gantry Crane Installation Guide

2026-09-14

General Overview

This guide specifies the standard installation procedures, 安全要件, and commissioning steps for double girder gantry cranes. It applies to industrial outdoor and indoor double girder gantry cranes used for material handling in factories, ポート, そして建設現場. All installation work must be performed by certified professional technicians in strict accordance with manufacturer specifications and national crane safety standards. Unauthorized modification of installation procedures is prohibited to avoid equipment failure, 構造的損傷, or safety accidents.

Double girder gantry crane installation guide

Double girder gantry crane installation guide

インストール前の準備

1. 現場検査 & Foundation Verification

初め, inspect the installation site to ensure the ground foundation meets the load-bearing requirements of the double girder gantry crane. Check the flatness, 硬度, and levelness of the foundation, and confirm there is no subsidence, 割れ目, or uneven settlement. Verify the installation spacing, track center distance, and overall dimension of the site match the crane’s design parameters. Clean up obstacles on the installation route and working area to ensure sufficient space for hoisting, 組み立て, and subsequent operation.

2. レールの設置 & 検査

Install the crane running rails strictly according to the design drawings. Fix the rails on the foundation embedded parts, adjust the rail levelness, 真直度, and gauge deviation to meet standard requirements. インストール後, conduct a comprehensive inspection: check rail connection firmness, weld quality, and end clearance; ensure no deformation or dislocation of the rails. Record all inspection data for subsequent acceptance reference.

3. Component Checking & Tool Preparation

Unpack all crane components including double main girders, 支持脚, エンドキャリッジ, traveling wheels, hoist trolley, 電気制御システム, ファスナー, and safety accessories. Carefully check each part for manufacturing defects, 変形, さび, または損傷, and verify the quantity and model of components are consistent with the delivery list. Prepare professional installation tools, hoisting equipment (auxiliary cranes, スリング, シャックル), measuring instruments (laser level, トルクレンチ, 巻尺), and safety protection supplies.

4. 安全への備え

Set up warning zones and safety barriers around the installation site, and post safety warning signs. All construction personnel must wear safety helmets, safety belts, and other protective equipment. Conduct pre-installation safety technical disclosure to clarify operation specifications, risk points, and emergency disposal measures. Confirm the power supply of the site is stable and grounded reliably to ensure safe electrical operation.

Double girder gantry crane installation guide

Double girder gantry crane installation guide

Main Mechanical Structure Installation

1. Ground Pre-Assembly

Complete partial pre-assembly of components on the flat ground to reduce high-altitude operation risks. Assemble the two main girders as a whole structure according to the assembly marks, fasten all connecting bolts with a torque wrench to reach the specified torque value. Install the walking platform, 手すり, and trolley running track on the main girders, and check the flatness and firmness of the track surface. Then assemble the supporting legs and end carriages into integrated parts respectively.

2. Supporting Leg & End Carriage Installation

Use qualified auxiliary hoisting equipment to lift the assembled supporting leg and end carriage assemblies vertically, and place them accurately on the reserved installation position of the running rails. Adjust the verticality, 水平性, and spacing of the supporting legs strictly, fix the traveling wheel boxes on the rails, and ensure the wheels are completely attached to the rail surface without deviation or suspension. Temporarily fix all connecting parts to prevent displacement during subsequent girder installation.

3. Double Main Girder Hoisting & Fixing

Adopt integral hoisting method for the assembled double main girders. Hang the slings at the designated lifting points of the girders to ensure uniform stress and balance during hoisting, and avoid tilting or structural deformation. Slowly lift the main girder assembly to the design height, align the connecting holes with the top of the supporting legs accurately, and carry out butt joint installation. After precise alignment, install and tighten all high-strength bolts in sequence, and use a laser level to recheck the levelness and span deviation of the main girders to ensure compliance with design standards.

4. トロリー & Hoisting Mechanism Installation

Place the assembled hoist trolley stably on the trolley track of the double main girders, adjust the trolley wheel gap and running parallelism to ensure flexible and jitter-free movement. Install the lifting mechanism, steel wire rope, プーリーブロック, and hook group in strict accordance with the mechanical assembly drawings. Check the winding direction and tightness of the steel wire rope to ensure no strand disorder, extrusion, または着る. Install buffer devices, limit stoppers, and anti-derailment devices at both ends of the trolley track.

Double girder gantry crane installation guide

Double girder gantry crane installation guide

Electrical System Installation

1. Electrical Component Installation

Install the main electrical control cabinet, trolley control box, resistance box, and operating device (pendant control or cab control) at the designated positions. Fix all electrical boxes firmly with shock absorption measures to prevent vibration damage during crane operation. Install travel limit switches, lifting height limit switches, 過負荷リミッター, and other safety electrical accessories, and ensure all sensor components are installed accurately and fixed reliably.

2. 配線 & Grounding

Lay cables strictly in accordance with the electrical wiring diagram, arrange cables neatly, and fix them with cable clamps to avoid dragging, extrusion, and friction damage. Connect L1, L2, L3 power lines, neutral line N, and protection grounding line PE correctly, and tighten all copper wire terminals firmly to ensure good electrical contact. Complete the grounding connection of the crane metal structure, and test the grounding resistance to ensure it meets safety standards, preventing electric leakage accidents.

3. Circuit Inspection

After wiring completion, conduct a comprehensive circuit inspection. Check for wrong wiring, missing connection, virtual connection, and short circuit risks. Verify the phase sequence of the power supply to ensure the walking and lifting directions of the crane are consistent with the control operation. Inspect the insulation performance of all circuits to ensure no insulation damage or electric leakage hidden dangers.

Double girder gantry crane installation guide

Double girder gantry crane installation guide

Debugging & 試運転

1. No-Load Debugging

Switch on the power after confirming all mechanical and electrical installations are qualified. Conduct no-load operation debugging: operate the crane’s longitudinal traveling, trolley transverse traveling, and lifting mechanism respectively. Check whether each mechanism runs smoothly without abnormal noise, jitter, or stuck phenomenon. Test the sensitivity and reliability of all limit switches, バッファデバイス, and safety protection functions, and adjust the limit stroke to the standard range.

2. 負荷テスト & 較正

After qualified no-load debugging, carry out graded load tests according to standard procedures, 含む 25%, 50%, 75%, 100%, そして 125% rated load tests. During the test, check the structural deformation of the main girders and supporting legs, the operating stability of each transmission mechanism, the braking performance of the brake system, and the accuracy of the overload protection device. Record all test data, and adjust and calibrate unqualified items until they meet the standard requirements.

3. Overall Performance Inspection

Inspect the overall operation coordination of the crane, confirm the synchronous operation of each mechanism, accurate control response, and reliable braking. Check the tightness of all connecting bolts, the lubrication state of transmission parts, and the integrity of safety accessories. Eliminate all installation defects and hidden troubles to ensure the crane’s overall performance meets design and safety operation standards.

Final Acceptance & Safety Notes

1. Completion Acceptance

Sort out all installation records, inspection data, テストレポート, and component qualification certificates to form a complete acceptance document. Conduct final acceptance jointly by the construction team, supervision party, and user party. The crane can only be put into formal operation after passing the overall acceptance and obtaining the crane use qualification certificate.

2. Daily Safety Operation Notes

Operators must receive professional training and hold valid certificates before taking up their posts. Strictly abide by the crane operating specifications, prohibit overload operation, oblique pulling, and random limit operation. Conduct daily inspection and regular maintenance of the crane’s mechanical structure, 電気系統, and safety devices to ensure long-term stable and safe operation of the equipment.

3. Post-Installation Maintenance

After installation and commissioning, lubricate all rotating and transmission parts comprehensively. Check and fasten all loose fasteners again. Clean the equipment surface, sort out installation tools and residual materials on site, and complete site cleaning and finishing work.

Double girder gantry crane installation guide

威華工場

前の記事:
もうない, すでに最新記事です

Get Solution & Price Right Now!

私たちはあなたのフィードバックを大切にします! あなたの特定のニーズに合わせてサービスを調整できるように、以下のフォームに記入してください.

名前:
* メール:
whatsapp / 電話番号:
プロジェクトの場所:
* メッセージ:

最新のコメント

テスファイ・メレセ・サイード:
40 トン ダブル ガーダー オーバーヘッド クレーン トロリー アセンブリ (完全な電気的および機械的付属品付き)
リカルド・アギラール・サイード:
クレーン改修工事の場合, あなたのウェブサイトにエアコンユニットを設置する必要があります。このソリューションを見つけました。. 冷却能力: 2.5 KWa 7.0 KW (8,500 a 24,000 BTU/時間) 暖房能力 (オプション): 2.0 KWa 6.0 KW Fuente de alimentación: 24DCで / 110Vy / 230Vy / 415Vy, 50/60 Hz (要件を指定する) 冷蔵庫: R410A またはエコロジー R134a
言った:
容量 50 TON AKS ARALIK 40 メーター 12 METRE KANCA ALTI RAY BOYU 250 メーター, 2 ポータルクレーンの数量
ヒューバート・パティーノ・サイード:
親愛なる威華鶴様, GPANTEC SACを代表してご挨拶, リマにあります, ペルー. 御社製12トンスナッチブロックのお見積りをお願いします. 天井クレーンの製品参照コードまたはシリアル番号は、 110220.075, スナッチブロックモデルは12/2t-40Mです. ご依頼中のスナッチブロックの画像を添付します. ご希望数量は1キットです. どうぞよろしくお願いいたします. 心から.
ラ・グランジュ・サイード:
拝啓, 現在、モノレール軌道上で稼働する電気チェーンブロック用密閉導体レールシステムのサプライヤーを探しています。. 以下の要件についてお見積りを提出してください: Project Scope Quantity: 8 independent lines Length: 80 meters per line Total length: 640 meters Electrical Requirements Supply voltage: 400 VAC Frequency: 50 Hz Number of poles: 4 定格電流: 最小 40 A Application Electric chain hoist Safe Working Load (SWL): 2,500 kg One hoist per line Outdoor industrial installation Protection Requirements Minimum protection class: IP43 Preferred protection class: IP54 or higher Please include in your offer Conductor rails Power feed sections Joint assemblies End caps Hangers and support brackets Current collectors Expansion sections if required Complete accessory list Documentation Required Technical datasheets. システム全体の IP 保護等級の書面による確認. IP43/IP54要件への準拠を証明する試験証明書または実験室報告書. 同様のクレーンの設置参考資料, モノレール, またはホイストアプリケーション. も記載してください: 納期. 製造国. 保証期間. インコタームズ. ラインごとおよびプロジェクト全体の価格の内訳. 前もって感謝します, セドリック納屋

関連するケース

whatsapp

お問い合わせ

[ボタン]ボタンをクリックして、WhatsAppで製品情報と見積もりを取得します.

見積もりを入手してください
whatsapp
問い合わせ