Double Girder Gantry Crane Installation Guide

2026-09-14

General Overview

This guide specifies the standard installation procedures, yêu cầu an toàn, and commissioning steps for double girder gantry cranes. It applies to industrial outdoor and indoor double girder gantry cranes used for material handling in factories, Cổng, và các công trường xây dựng. All installation work must be performed by certified professional technicians in strict accordance with manufacturer specifications and national crane safety standards. Unauthorized modification of installation procedures is prohibited to avoid equipment failure, hư hỏng cấu trúc, or safety accidents.

Double girder gantry crane installation guide

Double girder gantry crane installation guide

Chuẩn bị trước khi cài đặt

1. Kiểm tra hiện trường & Foundation Verification

Đầu tiên, inspect the installation site to ensure the ground foundation meets the load-bearing requirements of the double girder gantry crane. Check the flatness, độ cứng, and levelness of the foundation, and confirm there is no subsidence, nứt, or uneven settlement. Verify the installation spacing, track center distance, and overall dimension of the site match the crane’s design parameters. Clean up obstacles on the installation route and working area to ensure sufficient space for hoisting, cuộc họp, and subsequent operation.

2. Lắp đặt đường sắt & Điều tra

Install the crane running rails strictly according to the design drawings. Fix the rails on the foundation embedded parts, adjust the rail levelness, sự thẳng thắn, and gauge deviation to meet standard requirements. Sau khi cài đặt, conduct a comprehensive inspection: check rail connection firmness, weld quality, and end clearance; ensure no deformation or dislocation of the rails. Record all inspection data for subsequent acceptance reference.

3. Component Checking & Tool Preparation

Unpack all crane components including double main girders, chân đỡ, toa cuối, traveling wheels, hoist trolley, hệ thống điều khiển điện, ốc vít, and safety accessories. Carefully check each part for manufacturing defects, sự biến dạng, rỉ sét, hoặc thiệt hại, and verify the quantity and model of components are consistent with the delivery list. Prepare professional installation tools, hoisting equipment (auxiliary cranes, Slings, xiềng xích), measuring instruments (laser level, cờ lê mô-men xoắn, thước dây), and safety protection supplies.

4. Chuẩn bị an toàn

Set up warning zones and safety barriers around the installation site, and post safety warning signs. All construction personnel must wear safety helmets, safety belts, and other protective equipment. Conduct pre-installation safety technical disclosure to clarify operation specifications, risk points, and emergency disposal measures. Confirm the power supply of the site is stable and grounded reliably to ensure safe electrical operation.

Double girder gantry crane installation guide

Double girder gantry crane installation guide

Main Mechanical Structure Installation

1. Ground Pre-Assembly

Complete partial pre-assembly of components on the flat ground to reduce high-altitude operation risks. Assemble the two main girders as a whole structure according to the assembly marks, fasten all connecting bolts with a torque wrench to reach the specified torque value. Install the walking platform, tay vịn, and trolley running track on the main girders, and check the flatness and firmness of the track surface. Then assemble the supporting legs and end carriages into integrated parts respectively.

2. Supporting Leg & End Carriage Installation

Use qualified auxiliary hoisting equipment to lift the assembled supporting leg and end carriage assemblies vertically, and place them accurately on the reserved installation position of the running rails. Adjust the verticality, sự bằng phẳng, and spacing of the supporting legs strictly, fix the traveling wheel boxes on the rails, and ensure the wheels are completely attached to the rail surface without deviation or suspension. Temporarily fix all connecting parts to prevent displacement during subsequent girder installation.

3. Double Main Girder Hoisting & Fixing

Adopt integral hoisting method for the assembled double main girders. Hang the slings at the designated lifting points of the girders to ensure uniform stress and balance during hoisting, and avoid tilting or structural deformation. Slowly lift the main girder assembly to the design height, align the connecting holes with the top of the supporting legs accurately, and carry out butt joint installation. After precise alignment, install and tighten all high-strength bolts in sequence, and use a laser level to recheck the levelness and span deviation of the main girders to ensure compliance with design standards.

4. Xe đẩy & Hoisting Mechanism Installation

Place the assembled hoist trolley stably on the trolley track of the double main girders, adjust the trolley wheel gap and running parallelism to ensure flexible and jitter-free movement. Install the lifting mechanism, steel wire rope, khối ròng rọc, and hook group in strict accordance with the mechanical assembly drawings. Check the winding direction and tightness of the steel wire rope to ensure no strand disorder, extrusion, hoặc mặc. Install buffer devices, limit stoppers, and anti-derailment devices at both ends of the trolley track.

Double girder gantry crane installation guide

Double girder gantry crane installation guide

Electrical System Installation

1. Electrical Component Installation

Install the main electrical control cabinet, trolley control box, resistance box, and operating device (pendant control or cab control) at the designated positions. Fix all electrical boxes firmly with shock absorption measures to prevent vibration damage during crane operation. Install travel limit switches, lifting height limit switches, bộ hạn chế quá tải, and other safety electrical accessories, and ensure all sensor components are installed accurately and fixed reliably.

2. Đấu dây & Grounding

Lay cables strictly in accordance with the electrical wiring diagram, arrange cables neatly, and fix them with cable clamps to avoid dragging, extrusion, and friction damage. Connect L1, L2, L3 power lines, neutral line N, and protection grounding line PE correctly, and tighten all copper wire terminals firmly to ensure good electrical contact. Complete the grounding connection of the crane metal structure, and test the grounding resistance to ensure it meets safety standards, preventing electric leakage accidents.

3. Circuit Inspection

After wiring completion, conduct a comprehensive circuit inspection. Check for wrong wiring, missing connection, virtual connection, and short circuit risks. Verify the phase sequence of the power supply to ensure the walking and lifting directions of the crane are consistent with the control operation. Inspect the insulation performance of all circuits to ensure no insulation damage or electric leakage hidden dangers.

Double girder gantry crane installation guide

Double girder gantry crane installation guide

Debugging & Vận hành

1. No-Load Debugging

Switch on the power after confirming all mechanical and electrical installations are qualified. Conduct no-load operation debugging: operate the crane’s longitudinal traveling, trolley transverse traveling, and lifting mechanism respectively. Check whether each mechanism runs smoothly without abnormal noise, jitter, or stuck phenomenon. Test the sensitivity and reliability of all limit switches, thiết bị đệm, and safety protection functions, and adjust the limit stroke to the standard range.

2. Kiểm tra tải & Sự định cỡ

After qualified no-load debugging, carry out graded load tests according to standard procedures, bao gồm 25%, 50%, 75%, 100%, Và 125% rated load tests. During the test, check the structural deformation of the main girders and supporting legs, the operating stability of each transmission mechanism, the braking performance of the brake system, and the accuracy of the overload protection device. Record all test data, and adjust and calibrate unqualified items until they meet the standard requirements.

3. Overall Performance Inspection

Inspect the overall operation coordination of the crane, confirm the synchronous operation of each mechanism, accurate control response, and reliable braking. Check the tightness of all connecting bolts, the lubrication state of transmission parts, and the integrity of safety accessories. Eliminate all installation defects and hidden troubles to ensure the crane’s overall performance meets design and safety operation standards.

Final Acceptance & Safety Notes

1. Completion Acceptance

Sort out all installation records, inspection data, báo cáo thử nghiệm, and component qualification certificates to form a complete acceptance document. Conduct final acceptance jointly by the construction team, supervision party, and user party. The crane can only be put into formal operation after passing the overall acceptance and obtaining the crane use qualification certificate.

2. Daily Safety Operation Notes

Operators must receive professional training and hold valid certificates before taking up their posts. Strictly abide by the crane operating specifications, prohibit overload operation, oblique pulling, and random limit operation. Conduct daily inspection and regular maintenance of the crane’s mechanical structure, hệ thống điện, and safety devices to ensure long-term stable and safe operation of the equipment.

3. Post-Installation Maintenance

After installation and commissioning, lubricate all rotating and transmission parts comprehensively. Check and fasten all loose fasteners again. Clean the equipment surface, sort out installation tools and residual materials on site, and complete site cleaning and finishing work.

Double girder gantry crane installation guide

Nhà máy Vệ Hoa

Bài viết trước:
Không còn nữa, Nó đã là bài viết mới nhất

Get Solution & Price Right Now!

Chúng tôi coi trọng phản hồi của bạn! Vui lòng hoàn thành biểu mẫu bên dưới để chúng tôi có thể điều chỉnh các dịch vụ của mình theo nhu cầu cụ thể của bạn.

Tên:
* E-mail:
WhatsApp / Số điện thoại:
Vị trí dự án:
* Tin nhắn:

Nhận xét mới nhất

Tesfaye Melese đã nói:
40 Lắp ráp xe đẩy cần trục dầm đôi tấn với đầy đủ các phụ kiện điện và cơ khí
Ricardo Aguilar đã nói:
Đối với dự án cải tạo cần cẩu, Chúng tôi cần lắp đặt một bộ điều hòa không khí trên trang web của bạn, chúng tôi đã tìm thấy giải pháp này. Công suất làm mát: 2.5 KW một 7.0 KW (8,500 Một 24,000 BTU/giờ) Công suất sưởi ấm (Không bắt buộc): 2.0 KW một 6.0 KW Fuente de alimentación: 24Ở D.C. / 110V y / 230V y / 415V y, 50/60 Hz (Chỉ định yêu cầu) Tủ lạnh: R410A hoặc R134a sinh thái
Nói:
DUNG TÍCH 50 TON AKS ARALIK 40 MÉT 12 METRE KANCA ALTI RAY BOYU 250 MÉT, 2 SỐ LƯỢNG CẦU CỔNG
Hubert Patino đã nói:
Kính gửi Weihua Cranes, lời chào thay mặt GPANTEC SAC, tọa lạc tại Lima, Peru. Chúng tôi xin gửi yêu cầu báo giá Khối cẩu 12 tấn do các bạn sản xuất. Mã tham chiếu sản phẩm hoặc số sê-ri của cần trục là 110220.075, và mô hình khối giật là 12/2t-40M. Đính kèm hình ảnh khối cướp mà chúng tôi yêu cầu. Số lượng yêu cầu là một bộ. Chúng tôi rất mong nhận được sự quan tâm của bạn. Trân trọng.
La Grange Said:
Thưa ông hoặc bà, Hiện chúng tôi đang tìm kiếm nhà cung cấp hệ thống ray dẫn điện kín cho tời xích điện hoạt động trên đường ray đơn. Vui lòng cung cấp báo giá của bạn cho yêu cầu sau: Project Scope Quantity: 8 independent lines Length: 80 meters per line Total length: 640 meters Electrical Requirements Supply voltage: 400 VAC Frequency: 50 Hz Number of poles: 4 Đánh giá hiện tại: tối thiểu 40 A Application Electric chain hoist Safe Working Load (SWL): 2,500 kg One hoist per line Outdoor industrial installation Protection Requirements Minimum protection class: IP43 Preferred protection class: IP54 or higher Please include in your offer Conductor rails Power feed sections Joint assemblies End caps Hangers and support brackets Current collectors Expansion sections if required Complete accessory list Documentation Required Technical datasheets. Văn bản xác nhận xếp hạng bảo vệ IP của hệ thống hoàn chỉnh. Giấy chứng nhận kiểm tra hoặc báo cáo phòng thí nghiệm chứng minh sự tuân thủ các yêu cầu IP43/IP54. Tài liệu tham khảo lắp đặt cho cần cẩu tương tự, đường ray đơn, hoặc ứng dụng tời kéo. Hãy cũng cho biết: thời gian giao hàng. Nước sản xuất. Thời hạn bảo hành. Incoterms. Phân tích giá theo dòng và cho toàn bộ dự án. Cảm ơn trước, Nhà kho Cédric

Các trường hợp liên quan

WhatsApp

Liên hệ với chúng tôi

Nhấp vào nút để nhận thông tin sản phẩm và báo giá trên WhatsApp.

Nhận báo giá
WhatsApp
Cuộc điều tra